The posted speed limit is going to be 45 miles-per-hour through a busy stretch of Interstate 64 in Charleston beginning in the next few days through the end of October. The state DOH has hired a contractor to work on 19 interstate bridges.

Kokosing Construction Company will be paid $18.1 million to replace expansion joints, put down new concrete and strengthen existing bridge decks between the Brooks Street on-ramp and the Eugene A. Carter Memorial Bridge, part of the busiest stretch of interstate in the state.

 

DOH spokesman Brent Walker said most of the interstate system through Charleston is elevated and it's time to maintenance the many bridges that make up that system. He said traffic will be impacted day and night with through lanes being switched throughout the project.

Equipment will be moved into place beginning this weekend with the actual construction starting in early April. The project completion date is Oct. 28.

The DOH released the following information Thursday about traffic control set-up:

Friday, March 27th

8:00 p.m. to 10:00 a.m., Saturday

Two eastbound left lanes and westbound fast lane CLOSED to allow contractor to remove light poles and a section of the median barrier wall.

Saturday, March 28th

10:00 a.m. to 8:00 p.m.

Eastbound and westbound fast lanes CLOSED for work on median rumble strips/crossovers and placement of portable concrete barrier wall.

8:00 p.m. to 10:00 a.m., Sunday

Eastbound and westbound fast lanes CLOSED to complete placement of portable concrete barrier wall.

Sunday, March 29th

10:00 a.m. to 8:00 p.m.

Eastbound and westbound slow lanes CLOSED to perform work on outside shoulder rumble strips.